NSW council requirements

When a council asks for a quantity surveyor’s cost report.

Every NSW development application states an estimated development cost. Who may work that figure out depends on the amount, on the kind of development, and on the council. This page sets out what the state framework says and what 6 councils ask for, with the source and the date against each one.

The state framework

What Planning Circular PS 25-004 says

The circular sets one method for estimating development cost across NSW, and says who should work the figure out at each amount. Read the words it uses. They are not all the same strength.

Who can prepare the estimated development cost report in NSW, by estimated development cost
Estimated development costWho can prepare the report
Under A$100,000You, the applicant, or a suitably qualified person
A$100,000 to A$3 millionA suitably qualified person, such as a licensed builder, a registered architect, an accredited building designer or a quantity surveyor
Above A$3 millionA registered quantity surveyor, a member of the AIQS or RICS

That is the state rule under Planning Circular PS 25-004. A quantity surveyor is on its list of suitably qualified people in every band below A$3 million, and is the preparer it names above A$3 million.

Councils also set their own requirements, and some ask for a registered quantity surveyor well below A$3 million. A few set their own form and their own credential as well. Check your council's DA requirements before you lodge.

Under A$3 million the circular says the cost should be estimated by the applicant or a suitably qualified person, with the method submitted alongside the application.

Above A$3 million, and leaving aside state significant work, the circular says it is recommended that a report verifying the cost should be submitted, prepared by a qualified quantity surveyor who is a member of a relevant professional body. For state significant development and infrastructure the circular hardens that: a report prepared by an AIQS certified or RICS chartered quantity surveyor is required.

Above A$3 million the circular also asks for more than a signature. In its words, the report is to be prepared using the AIQS practice standard for estimating development costs, submitted in the standard form of quantity surveyor report available on the NSW Planning Portal, and based on cost estimates current as of that date and dated no earlier than 30 days from when the application is submitted.

The department's own estimated development cost page puts the same threshold more plainly. Its frequently asked questions say, in its words, that if your project's estimated development cost is over A$3 million you must submit a report, and that for projects under A$3 million a cost estimate report is recommended and councils set specific requirements for those reports.

Those two readings are not identical, and this page does not pick between them. A circular sentence is not a full legal answer, and neither is a website answer. Nothing here is legal advice. Check with your council, and take advice if the amount is near a threshold.

Who may prepare it

A quantity surveyor is one option of several

Below A$3 million the state framework does not ask for a quantity surveyor. It asks for a suitably qualified person, and it defines the term in a footnote.

The footnote lists a builder who is licensed to undertake the proposed works, a registered architect, a qualified and accredited building designer, a quantity surveyor, or a person who is licensed and has the relevant qualifications and proven experience in costing development works at least to a similar scale and type as is proposed.

So an architect or a licensed builder can prepare the estimate below A$3 million, and the state framework accepts it. The reason to buy a signed report below that amount is not that the state makes you. It is what your council asks for, and what an independent signature is worth when the figure is tested.

Council by council

What these 6 councils ask applicants to submit

A small list, each entry read from the council's own current document or page. Councils change these without notice, so treat every entry as true on the date shown and check the council before you lodge.

  1. Blacktown City Council

    Who may prepare the estimate

    A cost summary report is “Required for developments where the value of works are $3million or less”.

    A quantity surveyor’s report is “Required for developments where the value of works is more than $3million” and “Must be signed by a registered Quantity Surveyor”.

    When a quantity surveyor is asked for
    A quantity surveyor’s report where the value of works is more than A$3 million. At A$3 million or less, a cost summary report.
    GST, and which figure it applies to
    Two figures, not one. The council’s current estimated development cost report form follows Planning Circular PS 25-004, totals the elements “exclusive of GST”, and asks the signer to certify they “Excluded GST in the calculation of Estimated Development Cost (EDC)”. The older guide is about a different number: it applies “for the purpose of calculating the fees for the lodgement of a development application”, and for that figure it says “A genuine estimate is to include GST in the calculation.” A local development application fee is calculated on the cost plus GST, so a GST-inclusive figure is the fee-side total rather than the estimated development cost.
    Worth knowing
    Both documents are linked from the council’s own small scale residential development application page. The guide is the older of the two and still uses the pre-2024 term value of works. The estimated development cost form is the later one and is the one that cites PS 25-004.
    Source
    Read on 22 September 2026
  2. Central Coast Council

    Who may prepare the estimate

    For “Development up to $100,000” and for “Development with an estimated cost under $500,000”, “Council will accept a cost estimate prepared by the applicant or a builder’s quote”.

    For “Development with an estimated cost between $500,000 and $1 million”, “A suitably qualified person must prepare a cost estimate including the methodology used to calculate the cost.”

    For “Development over $1,000,000”, “Council will require a detailed cost report prepared by a registered Quantity Surveyor.”

    When a quantity surveyor is asked for
    A detailed cost report for “Development over $1,000,000”.
    GST, and which figure it applies to
    Excludes GST. The guide quotes section 6(2) of the Regulation in full, GST exclusion included, and its rate tables are footed “Based on costing for Sydney | Excluding GST”.
    Worth knowing
    A quantity surveyor is asked for above A$1,000,000, well below the A$3 million figure in the state circular. Read the boundary as the guide writes it: the applicant band is “under $500,000”, so A$500,000 exactly falls in the band above it. The guide still points readers to Planning Circular PS 24-002, which PS 25-004 replaced in October 2025.
    Source
    Read on 22 September 2026
  3. City of Sydney

    Who may prepare the estimate

    “$0 to $150,000: A cost summary report prepared by the applicant or a suitably qualified person.”

    “$150,000 to $3 million: A cost summary report prepared by a suitably qualified person.”

    “Over $3 million: An independent quantity surveyor detailed cost report verifying the cost.”

    When a quantity surveyor is asked for
    An independent quantity surveyor’s detailed cost report “Over $3 million”.
    GST, and which figure it applies to
    The page does not state a basis for the estimated development cost. It is written about fees, “Consent fees are based on the value of works proposed”, and it lists among the items to include in the development cost “Charges and fees: GST, Long Service Levy, development application fee, construction.” That is the fee-side figure, not the definition in section 6.
    Worth knowing
    The council publishes its own list of suitably qualified people, which is wider than the list in the state circular and adds a registered land surveyor and a practising qualified building estimator. The three XLSX forms themselves were not opened, only the page that describes them.
    Source
    Read on 22 September 2026
  4. Northern Beaches Council

    Who may prepare the estimate

    “Development with an estimated cost of up to $100,0000 is able to be estimated by the Applicant.”

    “Development with an estimated cost between $100,001 and $3,000,000 requires this form to be completed by a Building Industry Professional (Architect/Designer, Registered Builder).”

    “Development with an estimated cost over $3,000,001 requires this form or a Quantity Surveyors report to be prepared by a Quantity Surveyor (AIQS/RICS professional).”

    When a quantity surveyor is asked for
    The council’s own form, or a quantity surveyor’s report, prepared by a quantity surveyor for “Development with an estimated cost over $3,000,001”.
    GST, and which figure it applies to
    Excludes GST from the estimated development cost. The table foots “Estimated development cost (The sum of the above cost elements, exclusive of GST*)” with the note “Estimated development cost excludes GST, pursuant to Section 6 of the Environmental Planning and Assessment Regulation 2021”, then shows GST and the sum. The declaration’s separate line, “Included GST in the calculation of total development cost”, is about the other figure: the form says at the top that the estimate is used to calculate application fees under clause 256 and contribution levies under clause 208.
    Worth knowing
    “This form is required to be submitted with all Development Applications, except where there is no associated works.” Two things are worth reading carefully: the first band carries a typographical error in the source, “$100,0000”, and the bands as written leave A$3,000,001 itself between the second and third sentences.
    Source
    Read on 22 September 2026
  5. Randwick City Council

    Who may prepare the estimate

    The council’s development application page says “If the cost of your development is $500,000 or more, a detailed cost report will need to be prepared by a Registered Quantity Surveyor.”

    The cost report form it links says that where “the estimated development cost is less than $500,000”, “a Cost Summary Report is required (prepared by a suitably qualified person)”.

    The same form says that where “the estimated development cost is $500,000 or more”, “an Estimated Development Cost Report submitted in the standard form (prepared by a quantity surveyor who is a registered member of the Australian Institute of Quantity Surveyors) is required”.

    When a quantity surveyor is asked for
    A detailed cost report where the estimated development cost is “$500,000 or more”.
    GST, and which figure it applies to
    Excludes GST from the estimated development cost. The form’s table foots “(The sum of the above cost elements, exclusive of GST*)” with the note “Estimated development cost excludes GST, pursuant to Section 6 of the Environmental Planning and Assessment Regulation 2021”. Its declaration line “Included GST in the calculation of the total development cost” sits with a certification that the costs were calculated under section 6 and “in accordance with Section 208”, which is the contributions basis. The council’s page separately ties the cost summary report to “Council’s S94A development contributions plan”.
    Worth knowing
    This is the lowest trigger of the councils here, six times below the figure in the state circular, and it is the one council whose form sets its own credential. The form names three different standards in three places: a “registered member of the Australian Institute of Quantity Surveyors” on its cover, “an AIQS certified Quantity Surveyor or RICS chartered Quantity Surveyor” in the standard form section, and, two paragraphs later, “an appropriately qualified surveyor who is a member of a relevant professional body for example AIQS or RICS”. Those are not the same requirement. Ask the council which it will accept. The form also asks for the summary to use PS-24-002, which PS 25-004 replaced in October 2025.
    Source
    Read on 22 September 2026
  6. Wollondilly Shire Council

    Who may prepare the estimate

    “For DAs with development costs up to $100,000 the estimated cost can be supplied by the applicant or a suitably qualified person using the methodology set out in this guide.”

    “For DAs with development costs between $100,000 and $3 million, Council will require a cost estimate report from an independent, qualified builder, architect, building designer or quantity surveyor using the methodology set out in this guide.”

    “For development costs exceeding $3 million, a quantity surveyor’s cost report will be required.”

    When a quantity surveyor is asked for
    A quantity surveyor’s cost report “For development costs exceeding $3 million”.
    GST, and which figure it applies to
    Includes GST, and the guide is written about the fee figure: it opens by saying the Regulation “specifies that application fees for Development Applications are to be calculated on the ‘estimated cost’ of works”. On that figure it says a genuine estimate includes “All related Goods and Services Taxes”, and its rate tables are marked “Incl. GST”. The estimated development cost in section 6 excludes GST, so these are not the same number, and near A$3 million a project can fall on different sides of the line depending which one is used.
    Worth knowing
    The guide points to Planning Circular PS21-022 and PS21-020, both of which PS 25-004 replaced in October 2025, and it still uses capital investment value for regionally significant development. Ask the council whether its A$3 million line is read on its own GST-inclusive figure or on the estimated development cost.
    Source
    Read on 22 September 2026

Two of the 6 ask for a quantity surveyor well below the A$3 million figure in the circular. Randwick asks at A$500,000 or more. Central Coast asks above A$1,000,000.

Three are working partly from guidance the state has replaced. Wollondilly points to PS21-020 and PS21-022, and Central Coast and Randwick's own form point to PS 24-002. PS 25-004 replaced all three in October 2025.

Read the boundaries as each council writes them. Central Coast's applicant band is “under $500,000”, so A$500,000 exactly sits in the band above it. Northern Beaches writes “over $3,000,001” after a band that ends at A$3,000,000, which leaves A$3,000,001 itself between two sentences. Northern Beaches' own first band carries a typographical error, “$100,0000”. These are the councils' words, not ours, and they are quoted rather than tidied.

This is the honest state of it. You cannot answer the question from the state page alone, and no provider can tell you your council's threshold without reading your council's own document.

GST and levies

Three different numbers, and they are not interchangeable

Estimated development cost

Section 6 of the Regulation excludes GST from it. That is the figure that sets the approval pathway.

The figure behind the fee

For local and regionally significant applications the fee is worked out on the cost plus GST. The circular asks every estimate to show the cost, the GST and the sum of the two.

Section 7.12 levies

A separate basis under section 208 of the Regulation. The department states plainly that estimated development cost does not affect development levies.

This is why a council form can look as though it contradicts itself and does not. Four of the councils above use a form whose cost table is totalled exclusive of GST, citing section 6, and whose declaration asks the signer to certify that GST was included in the total development cost. Those two lines are about different numbers. The table is the estimated development cost. The declaration is the fee and levy total, which the same forms tie to clause 256 for fees and clause 208 for contributions.

Before you decide two documents disagree, check which of the three numbers each one is measuring. Wollondilly and Blacktown's older guide both write about the fee figure, and both say GST is included in it. That is the fee figure behaving normally, not a council rejecting the state definition.

Why buy one

What a signed report gives you

No report changes whether a council approves a development. These are the reasons that survive that.

  • A quantity surveyor is accepted at every state band

    The state framework names a quantity surveyor among the suitably qualified people who may estimate the cost below A$3 million, and names a quantity surveyor as the preparer above it. What that does not mean is that one report satisfies every council. Councils set their own forms, and Randwick sets its own credential: at A$500,000 or more its form asks for an AIQS certified or RICS chartered quantity surveyor. Read your council’s own document before you order.

  • The figure sits at arm’s length

    The estimate is prepared by someone who is not designing or building the project. That is worth something when a council tests whether an estimate is genuine.

  • The working is kept

    Every element is measured from your drawings and priced from a published rate. If a council queries a figure, there is a line to point at.

  • The state’s own form, completed

    The cost form from Planning Circular PS 25-004 is filled in with the same figures and signed, as an appendix to the report.

The offer

One signed report, A$999 inc GST

One price for any residential development application, whatever its size, with the state's cost form completed and signed.

Council cost report

A$999 inc GST

Any residential job, whatever its size. One development application, delivered within 24 hours.

  • The signed Estimated Development Cost Report, as a PDF
  • Prepared to Planning Circular PS 25-004 and the AIQS practice standard
  • Gross floor area measured to the AIQS method
  • An elemental estimate, with preliminaries and builder’s margin shown as their own lines
  • The state’s cost form from the circular, completed and signed
  • Reduced copies of your key drawings
  • GST shown excluded and included
  • Certified and signed by a registered quantity surveyor
  • Delivered within 24 hours
  • A reissue at no charge if your council names an item we missed
  • A tax invoice with every order
Order your report

If our quantity surveyor cannot certify a report from the documents supplied, we refund the order in full.

The report is prepared to Planning Circular PS 25-004 and the AIQS practice standard, and it is signed by a registered quantity surveyor.

If your council names a specific item we missed, we reissue at the corrected quantity at no charge.

Read the full example report

See how the report is made

How this page was checked

Sources, and what is left out

The state material is Planning Circular PS 25-004, issued October 2025, and the department's estimated development cost page, which shows an updated date of 13 May 2026. Both were read in full on 22 September 2026, and section 6 and section 208 were read in the Regulation itself.

Each council entry above links the council document or page it came from, with the date that document carries and the date it was read. Nothing on this page comes from a search summary or from another provider's article.

What was read and deliberately left off:

  • Sutherland Shire Council. Read and drafted in this pass, then withdrawn before publication because the entry could not be re-verified independently. The council’s origin returns HTTP 403 to every non-browser client from here, including its own landing page, and its PDFs download rather than render, so a second reader could not open either source document and confirm the bands word for word. The two URLs do resolve to real files, so the documents exist. But a document existing is not the same as its thresholds being quoted correctly, and a regulatory threshold published on a customer-facing page has to be confirmed rather than inherited. Re-add it only after someone opens both PDFs and checks the three bands against the text here.
  • Inner West Council. The council’s development application documentation requirements and its cost summary report form both return HTTP 410 Gone. The one current document that does open is a section 7.12 contributions form, the Detailed Cost Summary Report under the Inner West Local Infrastructure Contributions Plan 2023, which applies “where the development cost exceeds $1,000,000” and “can only be completed by a quantity surveyor who is a registered member of the Australian Institute of Quantity Surveyors”. A contributions levy is a different quantity from estimated development cost, and section 7.12 is expressly carved out of it, so that document cannot be reported as an estimated development cost threshold.

What this page does not do: it does not tell you whether a lender or an insurer will accept a report, because that was not checked. It does not cover any state other than NSW. It does not cover state significant development beyond naming it. And it is not legal advice.

Need the report for your application?

A$999 inc GST. Signed by a registered quantity surveyor, delivered within 24 hours.

24 hours from payment and a complete plan set, Monday to Friday. Orders after 2 pm Friday are delivered by Monday. Read the full terms.